Altech Chemicals awards German battery metals pilot plant engineering contract
Küttner will start engineering work immediately, with procurement and construction of the pilot plant to follow.
Company
ASX:ATC
Altech Batteries Ltd is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS to commercialise the revolutionary CERENERGY® Sodium Chloride Solid State Battery. CERENERGY® batteries are the game-changing alternative to lithium-ion batteries.
319 stories · page 2 of 4
Küttner will start engineering work immediately, with procurement and construction of the pilot plant to follow.
The company's potentially game-changing technology has demonstrated that silicon particles can be modified to resolve the capacity loss caused by swelling and first-cycle-loss capacity.
The key differentiation point of Silumina Anodes is that it will be a composite material of silicon and graphite particles that have been coated with alumina, using Altech’s proprietary alumina coating technology.
“Those forecasts, which will be refreshed and possibly changed for the February 1 board meeting, indicate that underlying inflation will print 2.25% by the end of 2022 and 2.5% by the end of 2023,” - Westpac.
The plant would produce alumina coated silicon/graphite anode materials to supply the lithium-ion battery and electric vehicle markets, using Altech’s proprietary coating technology.
The MoUs executed with SGL and Ferroglobe not only establish the basis for the possible future supply of high-quality feedstocks suitable for the battery materials coating process but also align with the objective to minimise the proposed p
Proceeds from the SPP, together with A$8.1 million from a recent placement, will be channelled into the construction of a battery materials coating plant in Germany.
The assessment is part of the PFS being undertaken by its 75%-owned German subsidiary Altech Industries Germany GmbH and ensures that it is now suitable for future green bond financing.
Funds raised will be applied towards construction of a pilot plant in relation to its battery materials coating technology in Saxony, Germany, the development of PFS and DFS studies, purchase of German land, and administration costs and for
Altech Chemicals has raised $8.1 million in an oversubscribed share placement. Together with capital from a share purchase plan, the company intends to use the cash to fund the next stages of construction for its battery materials plant in
"This major achievement is not just a significant breakthrough for Altech, but also for the lithium-ion battery industry generally. Especially so, given the 2020 public statement by US electric vehicle manufacturer Tesla, which said that it
If successful, commercialising Altech’s process would represent a significant step in lithium-ion battery anode evolution.
While the company is focused on completing funding for its high purity alumina (HPA) plant in Johor, Malaysia, it has its sights set on a second plant in Germany.
It is investigating the site as a preferred location for a second plant, specifically to service forecast HPA demand from Europe’s burgeoning electric vehicle and renewable energy battery sectors
Stage-1 and 2 early works construction activities have been completed with a total of 137,916 lost time injury (LTI) free hours at the site by the EPC construction team and its appointed subcontractors.
In response to the global COVID-19 pandemic, the Malaysian government imposed a Movement Control Order (MCO) effective from March 18.
The company has called for a minimum quality standard for all alumina used as coating material on battery separator sheets.
The assessment encompassed both project and governance aspects and allows the project to be considered by investors in the green bond market.
The company aims to become one of the world's leading suppliers of 99.99% (4N) high purity alumina (Al2O3) through construction and operation of an HPA processing plant at Johor, Malaysia.
A $200,000 initial payment will be made by Specialty Metals Investments in the coming days, which will represent a prepayment for Altech shares.
The company is confident most European governments will make an economic stimulus available once stability returns to financial markets.
The Centre of International Climate and Environmental Research (CICERO) is associated with the University of Oslo in Norway.
The company can produce high purity alumina at around a third of the price of traditional producers who use aluminium metal feedstock by instead using Kaolin from Meckering, WA as feedstock for the company’s plant in Malaysia.
In July 2019 Altech Chemicals sold an option to Frankfurt-listed Altech Advanced Materials AG (AAM AG), whereby the German entity can acquire up to a 49% interest in Altech’s project for US$100 million.
The substation is expected to be completed during April 2020 with major structural works now complete.
The company continues to work with its preferred mezzanine lender Macquarie Bank and with offtakers for product from the HPA processing plant in Malaysia, which is being constructed.
Feedstock for the company’s plant in Malaysia will be sourced from the 100%-owned kaolin deposit at Meckering, Western Australia.
A key step for the company's HPA strategy is a capital raise by Frankfurt Stock Exchange-listed Altech Advanced Materials AG of around €69.4 million if fully subscribed.
The company can produce HPA at around a third of the price of traditional producers who use aluminium metal feedstock.
The three-day event at the Esplanade Hotel Fremantle - by Rydges offers social and networking opportunities for delegates.
The demand for 99.99% high purity alumina (HPA) is likely increase further with the future development of solid-state lithium-ion battery technology.
The company aims to be one of the world's leading suppliers of 99.99% high purity alumina through construction and operation of a 4,500 tonnes per annum processing plant in Malaysia.
The agreement will see the Swiss-based bank act as placement agent in relation to issuing of equity or other equity instruments by AAM via private placement.
Hardware & electrical equipment
Remaining construction for the plant, which is subject to final funding, is expected to be 24-months with first HPA output anticipated in late 2021.
The company’s recent rights offer has been supported by Deutsche Balaton through a €1.2 million participation.
The Kerrigan project is 20 kilometres south of the central wheat belt town of Hyden, Western Australia, and covers an area of about 230 square kilometres.
The company is focused on developing a high purity alumina (HPA) plant located in Johor, Malaysia.
The company is focused on developing a high purity alumina (HPA) plant located in Johor, Malaysia.
Altech is aiming to become one of the world's leading suppliers of high purity alumina through the construction of a processing plant at Johor, Malaysia.
No corporate profit tax on business income until year 10 of operations which will have a positive impact on project free cash flow.
Remaining construction for the plant, which is subject to final funding, is expected to be 24-months, with first HPA output anticipated in late 2021.
The balance of the placement was supported by a range of professional and sophisticated investors, many of whom are long-term holders of Altech shares.
The halt will remain in place until Thursday, December 5, or until an announcement is released to the market.
If successful the raise would position AAM to exercise its option to acquire up to a 49% interest in Altech’s high purity alumina (HPA) project.
Altech’s preliminary investigation into the demand for high quality HPA from the EMC semi-conductor market indicates a global market size in the range of 700 – 900 tonnes per annum.
The company is focused on developing a high purity alumina (HPA) plant located in Johor, Malaysia.
Werner Klatten has held significant positions in the German media industry.
Construction of the substation structure is expected to begin during November 2019 once various off-site fabrication works are complete.
German engineering firm SMS group GmbH is the EPC contractor for construction of the company’s HPA plant in Malaysia.
German company Altech Advanced Materials will initially raise up to €69.4 million via rights issue and external share placement.
A European high purity alumina processing plant is part of the company’s strategic planning to benefit from the rapid transition to electric vehicles.
Altech is developing a high-purity alumina (HPA) project which involves building a HPA plant in Johor, Malaysia.
The company now holds a 29% interest in Altech Advanced Materials which in turn has obtained rights to acquire up to 49% of Altech’s high purity alumina project.
The company’s nominees have been appointed to German management and supervisory boards and the entity will be re-named Altech Advanced Materials AG.
The company is aiming to become one of the world's leading suppliers of 99.99% (4N) high purity alumina (HPA).
The advantage of this concept for Altech shareholders is that it provides an enhanced overall project and company valuation.
Cladding works are now underway with retaining walls construction nearing completion.
High purity alumina pricing is forecast to increase, driven by market developments in lithium-ion battery and other advanced applications such as LEDs.
Stage 1 construction progressing as planned with workshop steel frame erection nearing completion.
Altech recently raised the first steel at its high purity alumina (HPA) plant construction site in Malaysia.
The raising of first steel represents the culmination of a series of significant achievements for the project over the last six months.
Investments and investor services
The funds will enable the company to proceed with stage II engineering and construction at its Malaysian high purity alumina plant.
Hardware & electrical equipment
Attendees observed the progress made since the initiation of site works at Johor in late February 2019.
The company's securities will remain in trading halt until the start of trading on Tuesday, April 16, or when an announcement is released to the market.
Hardware & electrical equipment
The technology roadshow will stop by in Sydney on Tuesday, March 19, and in Melbourne on Thursday, March 21.
Hardware & electrical equipment
Workshop foundation piling is expected to commence shortly and preparations for the reinforced concrete works are in progress.
Petra Capital has a price target of 33 cents per share using a US$30,000 per tonne HPA price.
The company has started site establishment work at its high purity alumina (HPA) plant in Johor, Malaysia.
Hardware & electrical equipment
Achieving the go-ahead to proceed towards internal approval of a mezzanine debt facility is another important milestone for the company.
Investments and investor services
The event will attract “the who’s who of the junior and mid-cap market CEOs” and will have a “bustling exhibition area”.
A technical report prepared as part of debt due diligence has positive findings.
Approval of a development order paves the way for preparatory work before stage I construction of the Johor facility.
The two-day Technology and Low Emission Minerals Conference featured many of Australia’s emerging resource companies focused on sustainable operations and new energy minerals.
The company is commencing bulk earthworks and mobilising various sub-contractors, to maintain project momentum.
The conference will be held at the Westin Hotel in Perth next Tuesday and Wednesday, November 13 and 14.
The final design will be the basis for the submission of a development order application and the start of stage 1 construction.
A final investment decision study for ATC’s high purity alumina project was published in October 2017.
Hardware & electrical equipment
Five patent applications have been lodged in Australia, with one in examination phase, and two in Malaysia.
Investments and investor services
Regal Funds Management keynote speaker Julian Babarczy provides an overview of the battery metals sector.
Stage I construction of Altech’s Malaysian high purity alumina plant is already funded and will commence imminently.
Investments and investor services
The annual convention is on next week at the Hilton Brisbane with 48 presentations and 70 exhibitors.
Altech is equity funding stage I construction of its HPA plant in Malaysia in parallel with project finance close.
The company attended Battery Osaka in Japan, a conference which outlined shortages in medium-term high-purity alumina supply as well as the growing use of HPA in lithium-ion batteries.
Investments and investor services
Up to 600 investors hear from 21 companies at events in Sydney and Melbourne this week.
Around 600 investors will spend time at the Sydney event on Tuesday or at the Melbourne event on Thursday.
Hardware & electrical equipment
The company aims to become one of the world's leading suppliers of 99.99% HPA.
A due diligence kick-off meeting was held in Frankfurt, Germany on 27 July 2018.
Altech is starting stage I construction of its high purity alumina (HPA) plant in Johor, Malaysia.
Investments and investor services
Four companies will present at the luncheon events in Sydney and Melbourne.
Investments and investor services
Stage I construction at Johor site kicks off with a geotechnical drilling and ground survey program.
Seats are filling fast for this month’s luncheon series in Sydney and Melbourne.
Investments and investor services
Around 20% of the company’s shareholders participated in a share purchase plan at 16.5 cents a share.
Altech plans to feed the HPA plant using its kaolin mine in Western Australia.
Hardware & electrical equipment
EPC contractor SMS Group, of Germany, will undertake the work which is valued at about $10 million.
Archive
Funds to be applied towards the company's proposed high purity alumina (HPA) plant in Malaysia.
Funding will be used to commence construction of the high purity alumina plant in Malaysia.
Altech aims to be a vertically integrated producer of high-purity alumina (HPA).
The company's shares are trading about 6% higher intra-day, at 18 cents.
The company is aiming to construct a high purity alumina (HPA) plant in Malaysia.
The licence is for a 4,500 tonnes per annum high purity alumina plant.