Black Rock Mining negotiating to formalise government ownership in Tanzanian graphite project

The Tanzanian Mining Code and Regulations outline that all mining developments should make provision for government ownership via a 16% free carried interest.

Black Rock Mining Ltd - Black Rock Mining commences free carry interest negotiations with Tanzanian Government for Mahenge Graphite Project
Once finalised, the FCI will be held in the company’s Tanzanian operating subsidiary

Black Rock Mining Ltd (ASX:BKT) has received Tanzanian Government confirmation of the start of a process to formalise the structure and nature of ownership in the Mahenge Graphite Project.

The Government of the United Republic of Tanzania has provided written formal advice of the start of negotiations regarding its 16% free carried interest (FCI) in the project.

Black Rock managing director and chief executive officer John de Vries said: “The acknowledgement and commencement of a process to formalise the Government’s ownership in the Mahenge Graphite Project is a very significant milestone.

“Resolution of the structure and nature of our partnership with the Tanzanian Government through its negotiating team is a critical step in achieving financing conditions precedent.”

Shares are up almost 7% to 3.1 cents.

Government ownership

The Tanzanian Mining Code and Regulations introduced in 2017 outlined that all mining developments should make provision for government ownership via a 16% FCI.

De Vries said: “Black Rock is well prepared to follow the Government of Tanzania’s process with respect to the mining code and legislation.

“We look forward to progressing with formal engagement and completion of the FCI process.”

When the structure and nature of the FCI is resolved, the 16% FCI is expected to be held in the company’s Tanzanian operating subsidiary, Mahenge Resources Ltd.

Next steps

De Vries said the project would deliver benefits to host communities at Mahenge as well as to the Government of Tanzania and its people through the FCI.

He said: “We have an alignment of mutual interests which is a key objective of the FCI.

“At this stage, we are waiting on further advice of a planned date to commence the formal negotiation process and we confirm that we are at the beginning of the formal process.

“The company will continue to update our shareholders on the progress of our negotiations.”

Black Rock is progressing financing discussions and detailed engineering with a view to commencing project construction.

Mahenge resource

The project has a JORC-compliant mineral resource estimate of 212 million tonnes at 7.8% total graphite content (TGC) including ore reserves of 70 million tonnes at 8.5% TGC.

These ore reserves support a 16-year mine life of up to 350,000 tonnes of graphite per annum.

Quick facts: Black Rock Mining Ltd

Price: 0.053 AUD

ASX:BKT
Market: ASX
Market Cap: $33.86 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Black Rock Mining Ltd named herein, including the promotion by the Company of Black Rock Mining Ltd in any Content on the Site, the Company...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

Black Rock Mining agrees MOU with major Korean industrial group for Mahenge...

Black Rock Mining Ltd's (ASX:BKT) managing director and CEO John de Vries speaks to Proactive's Andrew Scott after signing a non-binding Memorandum of Understanding (MOU) with major Korean industrial group POSCO to form a strategic alliance and development relationship for the Mahenge Graphite...

on 10/6/20

2 min read