Tlou Energu looking for stability at Lesedi coal bed methane project

Gas and water are being produced at the Lesedi 3 and 4 production pods

Tlou Energy Limited -

Tlou Energy Limited (LON:TLOU) says rates of production from its Lesedi coal bed methane project in Botswana remain variable with gas flow rates fluctuating up and down.

Gas and water are being produced at the Lesedi 3 and 4 production pods, but having started at 20 Mscf (thousand standard cubic feet gas per day)  attempts to stabilise production at a higher rate of 80-100Mscf from each pod have been hampered by the changing flow rates.

WATCH: New PPA and funding update from Tlou in Botswana

Water extraction is also slowing the process though Tlou said it still has no reason to think it won't meet the higher target.

The company added it has submitted a request for an interim power purchase agreement to speed up the permitting process in Botswana, while it has received a non-binding proposal from the Botswana Development Corporation (BDC) to fund the first 10Mw of the project.

Other financing options are debt, equity and mezzanine finance. 

Quick facts: Tlou Energy Limited

Price: 2 GBX

AIM:TLOU
Market: AIM
Market Cap: £10.27 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Tlou Energy Limited named herein, including the promotion by the Company of Tlou Energy Limited in any Content on the Site, the Company...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

Tlou Energy's Tony Gilby hails receipt of interim power purchase agreement

Tlou Energy Ltd's (LON:TLOU) Tony Gilby speaks to Proactive London's Andrew Scott after confirming they've received an interim power purchase agreement (PPA) for its coal bed methane fuelled gas-to-power project in Botswana. He says the interim PPA has been agreed with the Botswana Power...

on 6/4/20

2 min read