Ncondezi Coal (LON:NCCL) has started to explore financing options for its 300 megawatt (Mw) power station in Mozambique after signing the power framework agreement earlier this year.
The finances will be finalised once commercial agreements have been agreed, said the company, but it envisages most being through debt with an equity contribution of 15-30%.
The new equity will be required only at the very end of the development stage and once the commercial agreements have been signed, the company said.
Ncondezi added that negotiating the commercial contracts - the Power Purchase, the Power Concession, the Coal Supply and the Transmission Access agreements – would now be its immediate focus.
Last year, Ncondezi made the strategic decision to switch from coal mining to power production and to build an integrated, long life, thermal coal power plant and open pit mine in phases of 300Mw units up to 1,800Mw.
The first 300Mw phase is expected to cost US$504mln, and be commissioned and generate electricity during 2017.
Production of an export thermal coal product and associated capital expenditure will now be initiated only when rail and port infrastructure in Mozambique is sufficiently advanced, Ncondezi added.
Paul Venter, chief executive, said, "Good progress was made during 2012 with Ncondezi completing all the major technical study work on the Ncondezi Project, including two DFSs on power and mine projects.
“The recent signing of the Power Framework Agreement with the Mozambican government formally endorsed the project and the company is busy advancing the heads of terms on the key commercial agreements, targeting completion by Q4 2013."
The company posted a loss after tax of US$8.6mln in 2012 and had cash and ewqivalents of US$12mln at the December year-end.