Buru Energy on fast-track to start new drilling program at Ungani Oilfield JV

The rig up, crew mobilisation and rig acceptance is on track for spud in the first week in May.
Mobilising the drill rig
Mobilisation of the NGD Loc 405 rig in Perth

Buru Energy Limited (ASX:BRU) is rapidly advancing preparations for a new drilling program at the Ungani Oilfield joint venture onshore in WA ’s southwest Kimberley region as it seeks to add to the oil bounty.

Preparations at the Ungani 6 well site have been completed with the drill pad liner installed and the drilling cuttings sump completed and lined.

Three wells planned

Site works at the Ungani 6 well location.

Work has also started on the Ungani 7 drilling pad which is adjacent to the Ungani 4 well, and this is expected to be completed shortly.

Civil works contractors will then start work on the Yakka Munga 1 well site at the JV with Roc Oil (Canning) Pty Limited in the Canning Basin.

Early site works at the Ungani 7 location.

These wells will be drilled with an NGD Loc 405 rig which is being transported to the site from Perth.

Mobilisation of the rig began on April 10 and is expected to be completed today with all 44 loads expected to be in place at the Ungani 6 well site by Saturday, April 13.

Containerised configuration

Loadout of the rig has been facilitated by its containerised configuration.

A rig support camp is being rigged up and the rig-up crew is due at the site today.

READ: Buru Energy to restart drilling efforts in June quarter

NGD Loc 405 will then be assembled, a task simplified by its modular nature, with a final acceptance inspection to be carried out before the well is spudded.

The section of the well to be drilled by the rig to the top of the Ungani reservoir is expected to take about three weeks to drill and case.

READ: Buru Energy buoyed by review which indicates strong gas and liquids potential for Butler conventional sand prospect

When this is completed, the rig will be moved to drill and case the equivalent pre-reservoir section on Ungani 7, after which the rig will move to the Yakka Munga 1 exploration well location.

Buru expects this sequence will be completed around mid-June when the Coiled Tubing Underbalanced Drilling (CTD-UBD) package will be mobilised to drill the underbalanced horizontal reservoir sections in Ungani 6 and Ungani 7.

All ground disturbing activities have been carried out under the on-site supervision of Traditional Owner heritage monitors.

View full BRU profile View Profile

Buru Energy Ltd Timeline

Related Articles

oil rig
November 19 2018
The core of the portfolio is in the East Midlands Basin, which includes the Wressle-1 oil discovery, a share of production from the Keddington oil field and a raft of drill-ready exploration and appraisal targets
Uranium
March 27 2019
The large scale uranium project has the potential to support a long life mining operation, with near surface, high-grade deposits for very low operating costs
coal mine
April 01 2019
Lesedi is one of two projects Tlou has in Botswana and comprises five CBM prospecting licences

© Proactive Investors 2019

Proactive Investors Australia PTY LTD ACN:132787654 ABN:19132787654.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use