Black Rock Mining test work in China validates Mahenge graphite flow sheet

The aim of the tests was to ensure Yantai could replicate and validate the unique Mahenge Graphite Project product attributes.

1554264848_Black-Rock-tests.jpg
The test work was designed to optimise the DFS flow sheet based on the first pilot program

Black Rock Mining Ltd (ASX:BKT) has completed pilot plant test works in China which have validated the optimised design flow sheet and concentrate properties for the Mahenge Graphite Project in Tanzania.

This work involved processing 18.5 million dry tonnes of ore in a dedicated pilot plant facility in China operated by Black Rock's EPC partner Yantai Jinyuan Mining Machinery.

Tests showed that the preliminary performance of recovery, grade and flake size is consistent with recent laboratory and definitive feasibility study (DFS) results.

READ: Black Rock Mining focuses on 2020 vision for Mahenge Graphite Project

The ore milled in the tests is characterised as Ulanzi oxide ores from Black Rock's 2018 bulk sampling program with pilot plant operations targeting production of the premium range of products.

Pilot plant operations were attended by Chinese, Korean and Japanese offtake and potential investment partners.

Black Rock's chief executive officer John de Vries said: “Our second round of substantial pilot plant test works is the best way to attract finance by further de-risking the project.

“This pilot plant has also given us an opportunity to differentiate and demonstrate the uniqueness of Mahenge brand graphite in front of key off-takers and potential investors.

“The demonstration of our capacity to produce our premium branded product through a simple and repeatable process without the need for chemical intervention establishes Mahenge as one of the world’s leading premium flake graphite concentrates.

“The pilot plant will deliver improvements on our DFS flow sheet by incorporating the experience and IP of Yantai Jinyuan and once all the plant data is fully processed, we will be able to proceed with contract establishment with Yantai Jinyuan for supply of plant and engineering services.”

Tests at the dedicated facility in Laiyang province, China.

Large flake (plus 100 mesh) concentrate will be made available to off-takers as part of the company’s validation process.

All sub 100 mesh flake will be processed for battery anode precursor in dedicated facilities to establish spheronising plant performance metrics and to provide increased volumes of material for independent battery performance testing.

Data from this work will be available in late May.

Quick facts: Black Rock Mining Ltd

Price: $0.07

Market: ASX
Market Cap: $42.16 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Black Rock Mining Ltd named herein, including the promotion by the Company of Black Rock Mining Ltd in any Content on the Site, the Company...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

Black Rock Mining adds fourth module to enhance graphite project DFS and...

Black Rock Mining Limited (ASX:BKT) chief executive officer John de Vries updates Proactive Investors on its enhanced Mahenge Graphite Project definitive feasibility study (DFS) which includes a fourth module to improve project metrics. The CEO says the eDFS brings together a number of...

3 weeks ago

3 min read