TLOU Energy advances second new Lesedi CBM well

The drill programme aims to add operational data to its 'compelling' coal bed methane project proposal in Botswana.
oil and gas operations
In October the Lesedi CBM proposal was sent to the Botswana authorities

TLOU Energy Ltd (LON:TLOU) updated investors on its field operations in Botswana where it is advancing the Lesedi coal bed methane project.

It told investors that the vertical Lesedi-3P well had now been drilled down to its total depth of 575 metres.

READ: Tlou Energy believes proposal for Lesedi is compelling

Drilling is also now underway for Lesedi-4P which is the second well in the current programme.

The aim is to unlock gas flow data ahead of the company’s proposed initial project development area. It is anticipated that production start-up for the wells could come in early 2019.

“The wells will be on production for an extended period of time to de-water and lower the pressure in the coal seam to achieve gas flow,” Tlou said in a statement.

View full TLOU profile View Profile

Tlou Energy Ltd Timeline

Newswire
September 18 2018

Related Articles

gas pipes
October 22 2018
GDC is working with Altaaqa and other equipment suppliers to fast track six generators
Greenland Minerals' project on a map
October 30 2018
The company is spearheading a campaign to reduce capital costs for its flagship project.
1542291002_5485566276_150f71870a_o.jpg
Thu
This party is offering financing alongside services for the OPL226 development project and is reported to have strong familiarity with the region.

© Proactive Investors 2018

Proactive Investors Australia PTY LTD ACN:132787654 ABN:19132787654.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use