Proactive Investors - Run By Investors For Investors

Ormonde Mining achieves “major milestone” in development of Barruecopardo tungsten project

The AIM-listed mining firm said commissioning had commenced for the turnkey crush and screen plant, with the first trial of waste rock carried out successfully
Primary crusher
Primary crusher commissioning at Barruecopardo

Ormonde Mining plc (LON:ORM) has achieved a “major milestone” in the development of its Barruecopardo tungsten project in Spain.

In an update for the project, the AIM-listed mining firm said during August commissioning had commenced for the turnkey crush and screen plant, with the first trial of waste rock through the primary crusher having been carried out successfully.

READ: Ormonde Mining still on time and on budget with Barruecopardo development

Ormonde added that the rest of the crush and screen circuit was complete and the installation of associated electric circuits was due to be completed by the second half of September.

Initial commissioning of the water treatment plant at the site had also been carried out, the company said, with major equipment and structure installations at the process plant also “well-advanced”.

The company’s chairman, Michael Donoghue, said process plant commissioning was now expected to commence in “early December”, later than originally expected, and to run through into January 2019 with the production of tungsten concentrates to begin in February.

Ormonde added that the project’s construction costs remained within the budget of €53.6mln.

The firm holds a 30% stake in the Barruecopardo project and has been pushing ahead with construction following a strengthening in tungsten prices last year in partnership with Oaktree Capital, who owns the remaining 70% stake.

View full ORM profile View Profile

Ormonde Mining plc Timeline

Related Articles

A map of the Wa project in far northwest Ghana along the border with Burkina Faso
March 06 2019
The JV partners also plan to make an investment decision on the Ghanaian project this year.
gold nuggets
January 22 2019
The company has received encouraging exploration results from across its East Pilbara projects in 2018.
Yaouré Gold Project in Côte d’Ivoire
April 03 2019
The company is expected to post its latest production figures later this month.

© Proactive Investors 2019

Proactive Investors Australia PTY LTD ACN:132787654 ABN:19132787654.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use