Volt Resources receives environmental certificate for flake graphite project in Tanzania

The company has passed one of the few remaining milestones in government permitting for the Bunyu project.

View over Bunyu project
North Pit at Bunyu will be on the rising ground in the foreground.

Volt Resources Ltd (ASX:VRC) has passed another key milestone in development of the Bunyu Graphite Project in Tanzania after receiving the Environmental Impact Assessment (EIA) Certificate.

This represents the final pre-requisite for the granting of Volt’s mining licence and one of the final remaining major milestones in terms of government permitting for the Bunyu project.

READ: Volt Resources gets ready for stage I development of Tanzania’s largest graphite resource

The company’s wholly-owned subsidiary Volt Graphite Tanzania Ltd received the certificate from the National Environment Management Council of Tanzania (NEMC).

It was signed by the Honourable Minister of State in Vice President's Office for Union Affairs and Environment January Makamba.

“Significant milestone”

Volt’s chairman Asimwe Kabunga said, “This is a significant milestone in the development of our Bunyu project, as it transitions the company a step closer to receiving the all-important mining licences.

“Volt would like to thank the local communities and government parties within the Lindi and Mtwara regions, along with the NEMC, our Tanzanian specialist consultants Tansheq Limited and their sub-consultants, and our staff for their support, commitment, tenacity and diligence throughout this important process.”

READ: Volt Resources cooperates with Chinese graphite company regarding Bunyu offtake

The Mining Licence Applications (MLAs) were submitted to the Minister for Minerals in February 2018.

Recently the Tanzanian Minerals Commission issued revised formats for the Integrity Pledge and Local Content Plan to be submitted with the MLAs.

These have been completed and lodged with the commission.

Mining licences expected soon

Once the EIA certificate is lodged with the commission the company expects the two mining licences to be granted soon thereafter.

The MLAs and EIA certificate, along with the approval of the resettlement compensation under the Resettlement Action Plan, covers the area required for the stage I development and stage II expansion project.

Kabunga said, “Looking ahead we remain firmly focused on advancing the Bunyu project towards stage I production.

“We look forward to providing shareholders with further updates on funding and development progress in the near-term.”

Quick facts: Volt Resources Ltd

Price: 0.018 AUD

ASX:VRC
Market: ASX
Market Cap: $34.18 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Volt Resources Ltd named herein, including the promotion by the Company of Volt Resources Ltd in any Content on the Site, the Company receives...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

Volt Resources strives to be leading natural flake graphite producer

Volt Resources Ltd (ASX:VRC) CEO Trevor Matthews details progress and aspirations for the Bunyu Graphite Project in Tanzania, as demand and supply for the commodity shifts, sending up prices. Speaking about a potential note issue on the Dar es Salaam Stock Exchange, Matthews says, "we're...

on 18/4/18

2 min read