Argosy Minerals produces first batch of lithium carbonate at Rincon Lithium Project

Progressing towards the stage 1 milestone - to produce a battery grade LCE product.

lithium brine ponds
Resource estimation work nearing completion

Argosy Minerals Limited (ASX:AGY) has achieved a significant milestone for its Rincon Lithium Project in Argentina by producing the first batch of lithium carbonate (LCE) from the stage 1 industrial scale pilot plant.

A sample of the first one-kilogram production batch was tested in Argosy’ lab and was determined to be a good quality industrial grade LCE.

Progressing stage 1 LCE product off-take agreements

Argosy is progressing with a major international group on the stage 1 LCE product off-take agreement.

The product quality and process test-works completed to date provides confirmation for Argosy to produce a consistent product that meets customer requirements.

The company will continue processing works to prepare these customer samples for their own quality confirmation and testing, and then for subsequent initial commercial sales.

READ: Argosy Minerals purchases mining tenements for future lithium brine operation

Argosy managing director Jerko Zuvela said: “We are delighted at this significant milestone, noting the historical magnitude of this achievement and the fast-track strategy the company deployed to attain this landmark development.

“The momentous effort, technical expertise and knowledge required to achieve this initial milestone is extraordinary, and I thank the whole Puna and Argosy team for their commitment and dedication.”

Upgrading the LCE to battery-grade

Importantly, key deleterious elements for battery grade in the test batch such as magnesium, sulphate and metallic impurities were within acceptable specification ranges.

The key issue determining the tested batch to be industrial grade vs. battery grade was the presence of certain soluble impurities.

These would usually be removed by the ‘washing’ stage but that stage is not yet fully functional in the plant because the stage prior requires a high heat, and Argosy is still awaiting a natural gas supply for the plant to provide such temperature.

The plant is physically connected to the local mains gas network but the company is waiting for local bureaucratic approval to switch on the supply, to then continue full processing works to produce the battery grade material.

JORC resource estimation work nearing completion

Argosy is nearing completion of the resource estimation works for the Rincon Lithium Project and is progressing on preparing the Preliminary Economic Assessment.

Quick facts: Argosy Minerals Ltd

Price: 0.055 AUD

ASX:AGY
Market: ASX
Market Cap: $56.07 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

FOR OUR FULL DISCLAIMER CLICK HERE

GTI Resources upbeat as it kicks off aircore drilling program at Niagara...

Rob Holm, senior consultant with CSA Global, speaks with Proactive Australia's Andrew Scott following the news GTI Resources Ltd (ASX:GTR) has started an initial aircore drilling program at Niagara Gold Project near Kookynie in WA. CSA Global's managing the project and Holm says a 60-hole...

8 hours, 15 minutes ago

2 min read