BHP Group Ltd (ASX:BHP) has outlined a US$3.2–4.1 billion estimate for the first stage of its Olympic Dam smelter and refinery expansion, detailing a major component of its South Australian copper growth plans.

An investor presentation released on Monday, 23 November, targets a final investment decision in the second half of 2027 and first production in FY2032. The estimate is in real US dollars, with the project subject to further study and approval.

The expansion supports BHP’s existing ambition to produce about 500,000 tonnes of copper annually in South Australia by 2035, potentially reaching 650,000 tonnes by 2040.

Processing investment takes shape

BHP plans a new primary smelting furnace and acid plant, conversion of its existing furnace, and additional copper and precious metals refining capacity.

Construction would take about three years. The company also reported that execution of the Prominent Hill expansion is complete, with commissioning scheduled for December.

The program was advancing before Monday’s update.

In July, BHP awarded China Nerin Engineering a design and supply contract worth more than A$200 million for key processing facilities. The supply component remains conditional on approval of the smelter and refinery expansion.

At that time, BHP said more than A$2 billion of projects were already in execution across its South Australian operations, including Prominent Hill’s haul shaft and Olympic Dam’s Southern Mine Area access tunnel.

Copper earnings strengthen

Copper SA produced 321,000 tonnes in FY2026, up 2%, while underlying earnings before interest, tax, depreciation and amortisation rose 65% to US$3.2 billion.

Higher copper prices supported earnings. Gold, silver and uranium credits, together with inventory movements, also lowered reported copper unit costs.

Across BHP, copper contributed 54% of group underlying EBITDA in FY2026 and generated US$6.9 billion in free cash flow.

Nearer-term production remains more restrained. BHP maintained FY2027 Copper SA guidance of 290,000–320,000 tonnes in its October operational review.

September-quarter output fell 16% to 60,700 tonnes, mainly following Carrapateena’s conveyor failure. BHP said the replacement belt was operating at full capacity by the review.

The next major milestone for the proposed smelter expansion is its 2027 investment decision.