Aspire Mining obtains approval from Mongolian Reserve Council for total Ovoot reserves in Mongolia

The company had $13.5 million in cash with no debt at the end of the March quarter and is well funded to complete the Ovoot Early Development Project (OEDP) definitive feasibility study and reach a decision to mine.
Aspire Mining obtains approval from Mongolian Reserve Council for total Ovoot reserves in Mongolia
First deputy of UBTZ Igor Milostnykh and Apsire Mining executive chairman David Paull at the signing of the corporation agreement

Aspire Mining Ltd (ASX:AKM) has obtained approval from the Mongolian Reserve Council (MRC) in relation to the Ovoot reserves at its Ovoot Early Development Project (OEDP) in Mongolia.

This follows the company’s submission incorporating and consolidating all past data and information on Ovoot.

Aspire received the results of a pre-feasibility study (PFS) for the early development of the world class Ovoot Coking Coal Project in February 2019 by first constructing a haul road able to deliver up to 4 million tonnes per annum of coking coal to the nearest rail head at Erdenet.

From there the coal can be railed north or south to export markets.

Aspire’s strategy is to progress with low capital intensity road-based development to deliver early production

Ongoing works also aims to advance the larger-scale and longer-term Erdenet-to-Ovoot railway development

Ovoot to Erdenet and the rail line from Tavan Tolgoi to Sainshand

 

READ: Aspire Mining substantial shareholder lifts stake to 27.49% from 16.1%

MRC approvals are required before the Detailed Environmental Impact Assessment (DEIA) can be undertaken and on completion, applications for mine permits and associated approvals can be made.

The company has a continuous engagement program to keep the local communities aware of the OEDP progress while outlining the positive impacts of employment, capacity building and infrastructure.

The local district and province have decided to combine road and mine approvals at the community level into one package, which has caused a delay in the company’s planned program to complete the DFA.

The completion of the DFS is now expected before the end of calendar 2019 with the timeframe for first coal production remaining mid-2021.

READ: Aspire Mining releases positive early development PFS as markets absorb high-profile coal takeover bid

Timeline to first production

 

Aspire expects to be in OEDP production by quarter-two 2021 with a 15-month haul road construction period beginning in late 2019 – early 2020.

Russian – Mongolian joint venture Ulaanbaatar Tumur Zam (UBTZ) owns and manages the Mongolian rail network and on May 24, 2019, Aspire and UBTZ executed a corporation agreement.

The agreement ensures an allocation by UBTZ to Aspire of rail line capacity from Erdenet to the Mongolian – China border at Zamyn Uud.

It guarantees up to 4 million tonnes per annum of rail line capacity will be available to the company in support of its OEDP requirements.

 

 

In 2014 the company conducted initial test work on blending Ovoot coking coal and identified a substantial opportunity to value add to Tavin Tolgoi’s non-coking coal resources through blending with Ovoot’s ‘fat’ coking coal.

Tavan Tolgoi is Mongolia’s largest coking coal mine and with the OEDP now presenting near-term production, Aspire and Tavan Tolgoi’s government owner Erdenes Tavan Tolgoi can take the next step in evaluating the opportunity.

Tavan Tolgoi is in the middle of an IPO process planned to occur later in the year.

Aspire is also currently forming a short list of potential international technology partners.

View full AKM profile View Profile

Aspire Mining Ltd Timeline

Related Articles

Pamlico project picture
June 24 2019
Newrange is earning into 100% of its flagship project via staged annual payments up to 2044
Cobalt symbol, Co
March 12 2019
Winmar is planning a London listing and intends to return to the ASX.
Inspection at Cangai property
April 29 2019
The company has the Cangai Copper Project in northern NSW as its flagship asset.