FYI Resources completes metallurgical drilling to advance BFS and upgrade kaolin resource

Six reverse circulation holes were extended to provide hydrological information to calculate the water supply for onsite beneficiation and to incorporate the hydrological results into an environmental study and mine plan.

RC drilling at Cadoux
Analysis of the drilling results are pending and is being performed by Intertek laboratories in Perth

FYI Resources Ltd (ASX:FYI) has completed the first phase of metallurgical drilling at Cadoux Kaolin Project in WA aimed at advancing a bankable feasibility study (BFS) and upgrading the measured resource to proven reserve status.

The program, which consisted of close spaced infill drilling of the current resource, was also designed to achieve key technical project objectives and provides further kaolin feedstock for continued metallurgical test work and pilot plant process studies.

READ: FYI to target deposit definition with drilling program at Cadoux Kaolin Project

Diamond drilling at Cadoux HPA Project

FYI managing director Roland Hill said: “The drilling went particularly well and we are very interested in integrating all of the results and applying it to our ongoing test work programs including the pilot plant.

“We will also be incorporating the information into our BFS and broader mine plan and environmental and permitting studies.

“To expedite FYI’s HIgh Purity Alumina (HPA) development timeline efficiently, the drilling will be utilised as the grade control determining the mining plan on the first phase of mining.

"The detailed drilling campaign is consistent with our strategy of delivering a world leading HPA project with the lead into production being de-risked.”

 

 

The reverse circulation (RC) component of the drilling program aimed to:

  • Support the current metallurgical model in terms of grade and variation of the deposit as a feedstock;
  • Increase confidence in the deposit leading to the conversion of the measured resource to a proven reserve for the first phase of mining; and
  • Provide grade control for the mining and increase the predictability of the future production schedule.

The drilling program consisted of 22 vertical (-90 degree) RC holes totalling 614 metres and generating 447 samples, as well as 4 angled (-70 degree) PQ triple tube diamond drill holes totalling 75 metres.

Samples were prepared at site and sent for a series of tests including standard kaolin suite analysis to determine the element grades and quality as well as to test the in-situ moisture of the kaolin.

Quick facts: FYI Resources Ltd

Price: $0.07

Market: ASX
Market Cap: $14.68 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of FYI Resources Ltd named herein, including the promotion by the Company of FYI Resources Ltd in any Content on the Site, the Company receives...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

FYI Resources commissioning high purity alumina pilot plant

FYI Resources Limited (ASX:FYI) managing director Roland Hill updates Proactive Investors on the commissioning of the high purity alumina (HPA) pilot plant at Kewdale, Western Australia. Hills says the plant is crucial in the development of the Cadoux Kaolin Project and he is happy with...

on 27/6/19

2 min read