FYI Resources to target deposit definition with drilling program at Cadoux Kaolin Project

The primary aim of the drilling program is to elevate the standard of input data to increase the technical and metallurgical understanding of the kaolin feedstock and assist in refining the process flowsheet design.
FYI Resources to target deposit definition with drilling program at Cadoux Kaolin Project
The drilling is expected to take one week to complete

FYI Resources Ltd (ASX:FYI) will begin a detailed drilling program at its Cadoux Kaolin Project in Western Australia this week to further define the deposit and augment the company’s high purity alumina (HPA) strategy.

The company has a planned program of about 1,200 metres utilising two rigs with a reverse circulation (RC) and diamond drill operating in sequence.

Samples generated and technical data obtained from the drilling is expected to provide important information for the bankable feasibility study expected to be complete in the September 2019 quarter.

 

FYI managing director Roland Hill said: “This drilling program is the next phase in advancing the development of the Caedouz Kaolin HPA Project.

“The technical accomplishments we have achieved in the development of our flowsheet design has provided us with excellent understanding of the intricacies of attaining such a high purity (99.999%) alumina product.

“We really want to now go back to the feedstock (kaolin) to develop a better understanding of the unique characteristics of the deposit and further de-rick the project and ensure quality control of the final product.”

The program is designed to accomplish several technical tasks including:

  • Increase FYI’s understanding of the mineral variability of the kaolin at Cadoux as well as its impact on potential HPA production;

  • Complete detailed ground water investigation as part of environmental studies;

  • Generate kaolin feedstock for FYI’s planned pilot plant;

  • Define the first phase of feedstock material for specific grade and mineralogy; and

  • Provide further samples for analysis to be included in the project database.

View full FYI profile View Profile

FYI Resources Ltd Timeline

Related Articles

Lithium Australia aspires to ‘close the loop’ on the energy-metal cycle
March 12 2019
Recent results show high-quality lithium-ion batteries can be generated from mine waste using its process.
Map of Queensland, Australia
March 01 2019
A recently published preliminary economic assessment shows an after-tax net present value of A$124 million and an internal rate of return of 24%
A 3D model of Black Rock Mining’s flagship project in Tanzania
Wed
The company is aiming to start production of graphite from its Tanzanian project in 2020.

© Proactive Investors 2019

Proactive Investors Australia PTY LTD ACN:132787654 ABN:19132787654.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use