Po Valley Energy moves step closer to gas production at Castello in Italy

au_italy350.jpg

Po Valley Energy (ASX: PVE) have achieved another milestone at the Castello gas field east of Milan.

Installation works on the Castello production field east of Milan have commenced.

Castello is 78% complete. First production is scheduled for late October 2009 - at an initial production capacity of 2.7 million cubic feet per day.

Italian contractor, Semat SpA, have commenced site activities today and expects to complete the civil works and plant installation within a target four-month schedule.

Po Valley Energy Managing Director, Michael Masterman said all production plant and equipment has been built, factory tested and awaiting completion of the 1st phase of civil works ready for installation.

"PVE is now in control of its development schedule for this field – a crucial hurdle for the Company,” Masterman said.

Quick facts: Po Valley Energy Limited

Price: 0.05 AUD

ASX:PVE
Market: ASX
Market Cap: $32.36 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Po Valley Energy Limited named herein, including the promotion by the Company of Po Valley Energy Limited in any Content on the Site, the...

FOR OUR FULL DISCLAIMER CLICK HERE

2 min read