Union Jack Oil PLC - West Newton Update and Investor Presentation
Market Abuse Regulation (MAR) Disclosure
Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement
("Union Jack" or the "Company")
West Newton Update and Investor Presentation
Rathlin included the following statements in its communication to local residents:
"
"The drilling rig and associated equipment have been demobilised from the site.
"The information acquired while drilling is currently being analysed to inform a well testing programme. Planning permission is in place for an extended well test. Any proposed testing programme would involve much less equipment on site than that required for the drilling programme.
"Recent articles in the local media and market releases from Rathlin's partners describing potentially the largest onshore hydrocarbon discovery since 1973, have many people in the local area naturally wanting to understand what the development of a commercial oil or gas field in the area might involve.
"We believe that speculating on the nature and size of a commercial development is premature at this stage, but early signs are encouraging. Firstly, the West Newton A-2 well must be completed and tested to gauge the productive potential for oil or gas from the Kirkham Abbey reservoir.
"Secondly, following the testing of the West Newton A-2 well, additional drilling at a new site (West Newton B) will be undertaken to establish the areal extent and continuity of the reservoir formation.
"Oil and gas, by their nature, would have different implications in terms of any potential development.
"Gas is typically gathered from wellsites and delivered by underground pipelines to local facilities or the national grid. Oil or other produced fluids may be trucked from sites to local facilities.
"The number and location of potential sites and number of wells per site required to develop a field would depend on a number of factors including
"Until the West Newton A-2 well is tested and we have an understanding of its productive capability it is premature to speculate on what any potential development may involve.
Once the testing operation commences it will take approximately 4-8 weeks. During operations the site will be manned by both operational and security personnel.
"Once test results are available and have been analysed, we will update our local neighbours and discuss the implications of those test results.
"At this time, Rathlin's planning permissions and EA permits allow for testing the wells at the West Newton A site. Any further drilling or production is not permitted and has not been applied for. Current planning permission and EA permits for the West Newton B site allow for site construction, drilling and testing of 2 wells. Additional drilling or production is not permitted and has not been applied for."
Union Jack Investor Presentation
Further details on PEDL183 and the West Newton gas discovery can be found in the investor presentation that will be used in an investor event starting at 18:30 today and will shortly be made available on the Union Jack website at www.unionjackoil.com.
For further information, please contact:
|
+44 (0)7787 160 682 |
|
|
|
|
|
+44 (0)20 3470 0470 |
Nominated Adviser and Broker |
|
|
|
|
|
|
|
|
+44 (0)7949 690 338 |
Public Relations |
|
Stefania Barbaglio |
|
This information is provided by RNS, the news service of the
The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of...
FOR OUR FULL DISCLAIMER CLICK HERE